DAC Enterprises Pty Ltd has a track record that confirms our ability to successfully complete civil construction projects whatever the environment. Our construction solutions are packaged to meet our clients’ requirements and expectations. Our commitment to quality outcomes and the development of excellent client relationships are key strategies of the company to ensure repeat business and superior project delivery.
Client : Department of Infrastructure
Contract Amount : $7.3 Mil
Location : Weddell
Completion date : January 2014
Project description: The works comprise the construction, testing and commissioning of a new transmission watermain along Jenkins Road and Channel Island Road consisting of the following items:
Client : Department of Infrastructure
Contract Amount : $2.2 Mil
Location : Percy Court, Alice Springs
Completion date : May 2013
Project description: Construction of Percy Ct Sewer Pump Station, and Associated Gravity and Pressure Pipelines
Works undertaken:
Pipeline Construction
Sewer Pumpstation Site Construction
Client : Power Water Corporation
Contract Amount : $5.1 Mil
Location : Katherine
Completion date : December 2012
Project description: Bulk earthworks, Concrete Construction Works & Pipe Works to extend existing treatment works
Works undertaken:
Client : Land Development Corporation
Contract Amount : $3 Mil
Location : East Arm NT
Completion date : January 2013
Project description: Bulk earthworks, Concrete Construction Work & Pipe Works
Works undertaken:
Client : Department of Construction and Infrastructure
Contract Amount : $300 K
Location : Tiger Brennan Drive Darwin
Completion date : July 2011
Project description: Remedial works to protect road batter formation from erosion by storm water runoff and tidal influence with the placement of Geotextile Fabric and Armour Rock Placement
Works undertaken:
This project was carried out along one of the main arterial roads to Darwin’s CBD and was implemented under full and uninterrupted traffic flow. This was successfully achieved by the design, documentation and implementation of an approved traffic control program. Delivery of armour rock to the site was carried out by the use of Road Train Side Tippers operating in this urban environment under strict traffic control guidelines.
The project was bounded by an environmentally sensitive urban mangrove stand with strict guideline and work area limitations imposed by the client to protect this fragile eco system. The tidal flows also placed limited time frames on work schedules. Despite these rigid environmental and site conditions the project was completed with nil incidents and within the project time lines.
Client : Land Development Corporation
Contract Amount : $21m
Location : East Arm Darwin
Completion Date : December 2011
Project Description : Construction of a 20 lot industrial subdivision.
Works Included:
Strict environmental guidelines were adhered to throughout the project duration as the project was located adjacent to the Darwin Harbour Foreshore Mangrove areas.
Together with this, some drainage structures were subject to tidal influence and therefore great care was required to prevent sediment and other contaminates entering the waterways feeding into Darwin Harbour.
Major earthworks were required to be carried out over a large area of the project with some heights of cut exceeding 10 M in depth. The material was unable to be free dug with conventional equipment so a Drill and Blast program was involved taking into account the close proximity to existing major commercial developments adjacent to the project. A total of 200,000 BCM of Drilling and Blasting was successfully carried out without incident during this operation. All blasting works were recorded with Video surveillance and state of the art shock wave monitoring equipment was implemented to confirm all blasts conformed to statutory regulations.